West Administration building doors covered for construction 8/2/2011
August 3-The dirt is getting moved.
The sidewalk between the 2 buildings is rubble now.
8/4/2011
Getting ready to install rebar.-8/21/2011
The "skeleton" of the building being prepared. 8/22/2011
Installation of piers. 8/31
Exterior wall of the Northside of the Sanctuary. 9/16
Connecting of the sewer line. 9/22
Breaking concrete forms. 9/30
The foundation of the outer wall. 9/30
The beginning stages of the monumental staircase. 10/18/2011
The foot of the staircase. 10/18/11
This will be covered in concrete by Sunday, October 23.
The beginning of the concrete foundation-10/20
10/26/11
10/26/2011
It will take a crane...
It's taking shape! 10/28/11
It looks like these guys are already bowing at the altar. :)
The stairway to nowhere (for now).
We have stairs!
More progress on the monumental staircase. 11/23
Man and machine working together.
A lot happened in 5 days! 11/28
11/30
12/09
It's beginning to look a lot like our new Sanctuary! 12/23
Preparing to lift a big piece of the puzzle. 12/29
Whoa! Southside truss being erected. 12/29/11
It's gonna take 2 cranes!
1/18/2012
1/20/12
Southside main girder truss. 1/20/2012